Wärtsilä & Vantaa Energy Signed an Agreement For Development Of A Power-to-Gas Plant

1025

The technology group Wärtsilä and Finnish utility, Vantaa Energy Ltd, have signed a co-operation agreement for pre-engineering and development of a Power-to-Gas (P2G) plant for Vantaa Energy. 

The plant planned to be commissioned in 2025 would be the largest in Finland and also the first to produce carbon-neutral, synthetic methane on a commercial scale with a fuel capacity of 10 MW. Synthetic methane is produced from captured carbon dioxide and hydrogen produced with renewable energy, says in article published on their website.

Aim of P2G plant

The EU has set a common target of climate neutrality by 2050, and has recently raised its emissions reduction target to 55% by 2030. Finland aims for carbon neutrality by 2035. The plant will represent a crucial step in Vantaa Energy’s decision to be fossil-free by 2026. 

Phasing out the use of fossil fuels utilising versatile technologies is an important enabler for carbon-neutral Vantaa Energy in 2030. The Power-to-Gas plant will allow Vantaa Energy to start using electricity produced from renewable sources for reducing CO₂ emissions in district heating, other applications where gas is used, and transportation.

Steps towards decarbonization

Wärtsilä will lead the pre-engineering phase of the project. Once completed, the project will produce synthetic methane from renewable electricity sources by extracting hydrogen from water, as well as extract CO₂ out of emissions from an existing waste to energy plant. The resultant methane will be sufficient for use in up to 200 trucks per day, and replace conventional, fossil natural gas in district heating during heating peaks in winter.

“The clock is ticking and we need to accelerate the move towards decarbonisation before it’s too late. This project showcases our vision of working towards a 100% renewable energy future, in which sector coupling and future fuels will play a decisive role. By cooperating with Vantaa Energy in this state-of-the-art project with us leading the pre-engineering, we are developing our Power-to-X technology and integration competences to meet future market needs. Collaboration with customers and other stakeholders supports our vision,” said Saara Kujala, General Manager, Business Development, Wärtsilä Energy.

Deadline for project

Wärtsilä’s pre-engineering work is expected to be completed by the end of 2022, and the project is scheduled for completion in early 2025. Once operational, the plant of Vantaa Energy will also highlight Finland’s support for the European Commission’s plans for the creation of a European hydrogen economy.

Summary

  •  Wärtsilä and Vantaa Energy, have signed a co-operation agreement for pre-engineering and development of a Power-to-Gas (P2G) plant for Vantaa Energy. 
  • Plant planned to be commissioned in 2025 would be the largest in Finland and also the first to produce carbon-neutral, synthetic methane on a commercial scale with a fuel capacity of 10 MW.
  • Finland aims for carbon neutrality by 2035 and plant will represent a crucial step in Vantaa Energy’s decision to be fossil-free by 2026.
  • Once completed, the project will produce synthetic methane from renewable electricity sources by extracting hydrogen from water, as well as extract CO₂ out of emissions from an existing waste to energy plant.